The pre-consultation for Terms of Reference for SIA and EIA for the Titanium Project at Pituffik

Project status of the Titanium project

Phase

Status

Date

The pre-consultation for Terms of Reference of the SIA and EIA reports

On-going

12  April to 19 May 2017

Minimum of 8 weeks of public consultation of the EIA and SIA reports (application for exploitation licence)

Pending

Update of the EIA and SIA reports

Pending

-

IBA

Pending

-

Granting of exploitation licence

Pending

-

Approval of exploitation and decommissioning plan

Pending

-

Approval of 1st plan of activities

Pending

-

Consultation material:

Bluejay Mining Ltd is the rights holder of exploration licence 2015/08 Northern Greenland. The pre-consultation is the company’s notification of the intention to apply for an exploitation licence for ilmenite.

    

Map Extract: Bluejay Mining Ltd exploration licence 2015/08 is marked in blue

The consultation material comprises the following documents (all in Greenlandic/Danish/English):

  1. Draft terms of reference for the Social Impact Assessment (SIA) -GL
  2. Draft terms of reference for the Environmental Impact Assessment (EIA) -GL
  3. Draft terms of reference for the Social Impact Assessment (SIA) - DK
  4. Draft terms of reference for the Environmental Impact Assessment (EIA) - DK
  5. Draft terms of reference for the Social Impact Assessment (SIA) - ENG
  6. Draft terms of reference for the Environmental Impact Assessment (EIA) - ENG

 

In the consultation material, the company’s name is FinnAust Mining Plc. FinnAust Mining Plc. was the name of the parent company and majority shareholder in the rights holder company Bluejay Mining Ltd. On 11 March 2017 the parent company decided to change its name to Bluejay Mining Plc.

 

As a result of the company intending to apply for an exploitation licence, at the end of March the company applied to transfer licence 2015/08 from Bluejay Mining Ltd. to a newly established limited company Dundas Titanium A/S, based in Greenland.

 

If the transfer is approved by the Government of Greenland before the expiry of the pre-consultation period, the name Dundas Titanium A/S will appear in the final Terms of Reference.

 

The pre-consultation can be regarded as a formal acknowledgment of the fact that the company wants a Social Impact Assessment (SIA) and an Environmental Impact Assessment (EIA) process to be implemented. The notification takes place by the company informing the authorities hereof and enclosing the draft Terms of Reference for the SIA and EIA reports respectively. Additional information about the process of preparation of SIA report and EIA report is available from “Social Impact Assessment - Guidelines on the process and preparation of the SIA Report for mineral projects”  and ”Guidelines for preparing an Environmental Impact Assessment (EIA) report for mineral exploitation in Greenland”

 

Draft Terms of Reference for the SIA and EIA reports shall, in accordance with the Mining Act, be sent in a pre-consultation for 35 days. Based on input from the pre-consultation, the company will determine the final content of the Terms of Reference and the subsequent draft SIA and EIA reports.

 

The consultation material does not contain information on the forthcoming division of Qaasuitsup Kommunia municipality. The company will, however, be requested by the authorities to mention the work concerning the forthcoming division in the final terms of reference, and to incorporate the new municipality structure to the extent relevant in the SIA and EIA reports that the company plans to prepare subsequently.

 

The consultation responses received in the course of the pre-consultation shall be treated equally with consultation responses received during the 8 weeks of public consultation of the reports will be included in a white paper. The company will prepare two white papers during the EIA and SIA process. One in extension of the consultation on the draft Terms of Reference and one for the 8-week consultation period on the draft reports The white papers are documents that contains important consultation comments, responses to these and a note on how relevant comments and suggestions will be incorporated into the final versions of respectively the Terms of Reference and the EIA and SIA reports.

 

The consultation deadline: 19 May 2017 at 4 p.m.

 

Consultation replies should be sent to The Mineral Licence and Safety Agency (Råstofstyrelsen), P.O. box 930, 3900 Nuuk or mlsa@nanoq.gl with a copy to isiin@nanoq.gl and eamra@nanoq.gl

Subject:

Raw materials

Hearingtype:

Environmental Assessment

Published:

12 april 16:00:00

Deadline:

19 maj 16:00:00

Send your answer to: